Myles Standish Hall – Construction Activity – Week of 5/16/16

For the week of May 16, 2016:

 Deliveries

  • Subcontractors will receive deliveries all week from 7 a.m. to 5 p.m. on both Beacon Street and Bay State Road.

Beacon Street Re-Striping

  • Our site subcontractor will be re-striping Beacon Street as required to make room for our Jersey barriers. (Per BTD this striping work will need to be done on off-hours.)

Mobilize – Safety orientations all week

  • Exterior – Beacon/Bay State/Point
    • Mobilize and site setup
    • Remove overhead protection on Bay State Road and Beacon Street in Phase 1 construction area
    • Installation of fencing and Jersey barriers
    • Removal of trees around building
    •  Load safety rails to roof and materials for temporary walls by crane staged at point park
  • Interior
    • Mobilize/protection/temporary walls
    • Install temporary fire alarm, temporary power, and temporary lighting
    • Decommission freight elevator

 Man and Material Hoist Construction

  • Install ties off of boom lift with white alarm on Beacon street (exterior work)

Demolition Abatement

  • Start demolition of stairway for chute
  • Start setting up for abatement of 9, 1, and basement
  • Demo 1st floor and Beacon Street exterior wall for load out
  • Annex – Start interior demo of basement and 1st floor for 1-story demo

Mechanicals

  • Make safe/cut and drop – Myles and Annex (1 story demo)
  • Start to separate utilities from Phase 1 side to occupied side of building

 Masonry Restoration

  • Mobilize with equipment to get ready for staging setup

For questions, please contact Brian Kelley.