Myles Standish Hall – Construction Activity – Week of 5/16/16
For the week of May 16, 2016:
Deliveries
- Subcontractors will receive deliveries all week from 7 a.m. to 5 p.m. on both Beacon Street and Bay State Road.
Beacon Street Re-Striping
- Our site subcontractor will be re-striping Beacon Street as required to make room for our Jersey barriers. (Per BTD this striping work will need to be done on off-hours.)
Mobilize – Safety orientations all week
- Exterior – Beacon/Bay State/Point
- Mobilize and site setup
- Remove overhead protection on Bay State Road and Beacon Street in Phase 1 construction area
- Installation of fencing and Jersey barriers
- Removal of trees around building
- Load safety rails to roof and materials for temporary walls by crane staged at point park
- Interior
- Mobilize/protection/temporary walls
- Install temporary fire alarm, temporary power, and temporary lighting
- Decommission freight elevator
Man and Material Hoist Construction
- Install ties off of boom lift with white alarm on Beacon street (exterior work)
Demolition Abatement
- Start demolition of stairway for chute
- Start setting up for abatement of 9, 1, and basement
- Demo 1st floor and Beacon Street exterior wall for load out
- Annex – Start interior demo of basement and 1st floor for 1-story demo
Mechanicals
- Make safe/cut and drop – Myles and Annex (1 story demo)
- Start to separate utilities from Phase 1 side to occupied side of building
Masonry Restoration
- Mobilize with equipment to get ready for staging setup
For questions, please contact Brian Kelley.