CILSE – Construction Activity – Week of 5/8/16
For the week of May 8, 2016:
On the Commonwealth Avenue side of the building, the team will continue replacing some of the glass units. Air and vapor barrier installation will continue on the Cummington Mall side, as well as the installation of window frames. On the Morse Auditorium side, there will be framing and sheathing from the swing staging, and the team will begin the installation of the air and vapor barrier from the mast climber. On the roof, the team will continue to frame, sheath, and flash the perimeter parapet walls.
Wall framing will continue on floors 7, 8, and 9. Installation of in-wall electrical and plumbing and above ceiling electrical, mechanical and plumbing will continue on floors 2 through 8. The team will continue to install drywall on floors 2, 3, and 4.
Police details will continue to man the construction gates along Commonwealth Avenue to ensure public safety. The safety of our community is our highest priority, so we ask that you please pay close attention to posted signs, police, and safety personnel.
For questions please contact Brian Kelley.